Situation
Our client, Russia’s largest underground mine, which uses a sublevel mining method, was struggling to deliver its production programme consistently and risked missing its ambitious production growth targets for the following year. Management engaged our team to conduct a diagnostic review and implement an operational improvement programme to achieve the planned performance levels.
What we did
- Developed and implemented more than 20 tools to plan and monitor mining operations from quarterly to shift level, covering production areas, underground haulage, mine development and support areas.
- Reduced instances of equipment and personnel being allocated inefficiently to faces where the work area or supporting infrastructure was not ready.
- Trained all line personnel, including foremen, in the new approaches and tools.
- Conducted an operational diagnostic review, developed driver models and identified bottlenecks and improvement opportunities.
Results
- 10% increase in production volume over 8 months of the project.
- 20% improvement in adherence to the monthly face-by-face production plan.
Production rate, % of baseline