Situation
Our client, Russia’s largest mining company, wanted to improve the productivity of a contractor carrying out capital mine development to open up a new production level at an underground mine, as part of a wider productivity improvement project. At the start of the project, development of the new production level was significantly behind schedule, and operational areas were consistently missing their daily targets because of organisational issues. Management engaged our team to develop and implement initiatives to accelerate mine development.
What we did
- Developed and implemented mine development cycle schedules tailored to the face categories.
- Developed productivity models for the main activities, including drilling, ground support and haulage.
- Developed and implemented tools to plan and monitor mining operations from monthly to shift level, minimising delays caused by organisational issues.
- Introduced a system of production meetings with standard agendas and visual materials.
- Developed and implemented a production reporting system covering shifts, days, weeks and months.
Results
- 112% increase in mine development rates following the introduction of cycle scheduling.
Capital mine development volume, thousand m³/month