Situation
Our client, a major vertically integrated Russian non-ferrous metals producer, was expanding a processing plant. Progress was slow, partly because of low contractor workforce productivity. The client brought in our team to deliver a comprehensive programme to improve its capital project management system, with a dedicated workstream to develop the contractor’s capabilities.
What we did
- Introduced processes for preparing monthly schedules broken down by day with a two-month planning horizon, tools to assess readiness to start construction and installation works, and trackers for material and equipment deliveries.
- Created a register of more than 70 risks and implemented measures to mitigate their impact.
- Introduced shift planning and performance reviews, as well as joint client–contractor site walkdowns to monitor work.
- Held a series of idea-generation sessions, leading to the development and implementation of more than 10 initiatives to accelerate foundation construction and structural steel erection.
- Adjusted the contractor’s organisational structure and replaced engineering and technical staff in both site-level and management roles.
Results
- 118% increase in contractor workforce productivity over 16 weeks of the project.
- 15% increase in productive working time for frontline personnel.
Workforce productivity, %