Situation
Our client, a major underground metals mining company, faced ineffective short- and medium-term mine planning. The main issue was that mine personnel focused on immediate targets, while metal grade targets were not being met and compliance with the production plan by mining unit was below target. Our team's objective was to develop an operational and medium-term planning model, then automate it and implement it at the company's main mines to ensure delivery of the production plan.
What we did
1. Developed the methodology
- Developed an operating model for the planning centre, including target-state process maps for medium- and short-term planning, in-shift dispatch and monitoring of mining activities; responsibilities across related functions; a cascade of performance review meetings; and KPIs.
2. Developed an IT solution to automate the processes
- Developed a prototype short-term planning system using Excel, VBA and an SQL database.
- Implemented a linear optimiser, followed by a non-linear optimiser, for an objective function based on the tonnage target and target blend.
- Developed and implemented integration through the client's data bus, linking MineSched, the 10-day and shift planning system, dispatch systems and mine supervisors' tablets.
- Rewrote the software in C#.
3. Implemented the processes and IT solution
- Staffed the mine planning and control centre in line with its organisational structure.
- Implemented the new processes and trained the planning centre team.
Results
- 12% increase in mine output.
- 20+% improvement in compliance with the monthly plan by mining area (mining unit).
- 10+% increase in equipment productivity by reducing inefficient equipment allocation to faces where the work area and/or infrastructure were not ready.
Monthly output at the largest mine, % of baseline
