Increasing longwall productivity at a Russian coal mine by 16%

Anton
Anton
Senior Partner
Yury
Yury
Associate Partner

Situation

Our client, one of Russia’s largest coal mines and part of a mining and metals group, was tasked with exceeding an already ambitious budgeted coal production plan. The main challenges were substantial unplanned downtime and longwall system productivity well below its rated capacity. Our team was engaged to improve maintenance performance and reduce the duration of operating tasks.

What we did

  • Reduced unplanned downtime by 49% through technical measures: a comprehensive inspection of the table hydraulic systems; restoration of the face-drive alignment system; replacement of the shearer’s upper and lower cutting drums and trapping shoes; replacement of the hydraulic power-pack unit; and installation of a device to shape the flow of mined material.
  • Reduced cycle time by 7% by shortening end-of-face operations.

Results

  • 16% increase in average longwall productivity per shift.
  • 9% increase in available operating time.

Examples of results

Average daily unplanned longwall downtime: 7.0 hours in the baseline period and 3.5 hours in the final project month, annotated −49%.

Average longwall cycle time: 141 minutes in the baseline period and 131 minutes in the final project month.