Increasing project NPV by 320% over baseline for an 8-million-tonne throughput expansion at a copper-molybdenum mining and processing operation in the CIS

Anton
Anton
Senior Partner
Anatoly
Anatoly
Associate Partner

Situation

Our client, a major copper-molybdenum mining and processing operation, was implementing a project to increase ore throughput by 40%. The project included constructing a new processing plant building, developing reservoirs to supply water to the plant and expanding the tailings facilities. Despite the substantial scope of work planned, the client had neither a dedicated project management team nor an overall master schedule setting out the project delivery timeline. Our team was engaged to increase project NPV by optimising design solutions and developing measures to shorten construction schedules.

What we did

  • Optimised the commissioning plan for water-supply facilities by deferring projects and eliminating those that were not required.
  • Developed measures to mitigate technical, environmental and legal risks.
  • Identified the project’s critical path, taking account of the delivery of a portfolio of more than 15 subprojects.
  • Developed recommendations to improve the project management system.

Results

  • 320% increase in project NPV.
  • 3% increase in potential throughput.
  • 10-month reduction in construction time for the facilities.

Increase in project NPV, % of baseline

Waterfall chart of baseline project NPV and the contributions of throughput, construction schedules, initiative delivery scenarios and risk mitigation.

× Enlarged image