Increasing the production rate at an underground mine by 48% by introducing a mining work schedule

Situation

Our client, a mining and processing operation in the CIS, had converted one of its remote mines from open-pit to underground mining using a sublevel mining method. The client did not have enough qualified planning personnel, and its limited equipment fleet was insufficient to meet its stretch production targets. Management engaged us to conduct a diagnostic review and improve the planning system to achieve those targets.

What we did

  • Reviewed and analysed the existing planning system.
  • Introduced a mining work schedule that enables the operation to:
    • Provide work areas for the entire available equipment fleet while allowing for planned equipment maintenance.
    • Track progress against the plan daily and take corrective action.
    • Link the production plan to equipment allocation based on agreed parameters, including haul distances, productivity and net operating time.

Results

  • +48% increase in the production rate through the introduction of the mining work schedule.

Examples of project outputs

Mining work schedule examples and a weekly production-rate chart showing a 48% increase.