Situation
Our client, a major vertically integrated mining and metals company, set out to increase development rates to raise production at one of its assets. Our team was engaged to identify and then implement initiatives to accelerate mine development.
What we did
1. Increased available working time by 48%–165% through:
- Assigning specific work orders to ensure damaged conveyor belt sections were replaced on time.
- Daily monitoring of the completion and status of gas drainage actions.
- Weekly checks to ensure personnel reached their workplaces on time and a day’s supply of materials was delivered to the face, reducing downtime caused by coordination problems.
2. Reduced development cycle time by 9%–15% through:
- Shortening the shuttle car haulage route by installing and extending the conveyor in crosscuts.
- Providing enough compressed air to operate two drilling rigs simultaneously.
- Replacing the shuttle car with a transfer unit and belt conveyor.
Results
- Achieved a 70%–180% increase in development rates with the existing equipment fleet and workforce.
- A 7% increase in coal production from faster development for the longwall.
Available working time, hours per day

Development cycle time, minutes per cycle