Situation
Our client, a major vertically integrated mining and metals company, set out to shorten longwall relocations to improve mine productivity. Our team was engaged to develop a package of initiatives to optimise the work schedule and reduce the duration of relocation activities.
What we did
Implemented the following initiatives:
- Conveyor dismantling: worked from both ends simultaneously and ensured components were kept intact.
- Support recovery: used a Petitto Mule recovery unit; created passing bays to specified dimensions to shorten the transport cycle; and allocated additional resources to building timber cribs and delivering timber.
- Support transport: introduced dispatch control, equipped diesel locomotives with spare parts and tools, and applied standard work procedures for receiving and transporting supports.
- Commissioning: carried out advance assembly in a dedicated passing bay near the installation chamber, installed cables along the longwall in parallel with the supports, and delivered materials and positioned equipment in advance.
Results
- A 5% increase in production from faster longwall relocations.
- A 9%, or 12-day, reduction in relocation duration.
Reduction in the time to recover 14 supports, days

Reduction in longwall relocation duration, days