Situation
Our client, a large mining and metals company, was experiencing slow mine development, which was affecting the start-up date for a new longwall face. We were engaged to develop initiatives to increase development rates and bring the new longwall face into production sooner.
What we did
- Analysed all work carried out by the client’s employees and contractors in detail.
- Analysed the interdependencies between processes, including safety requirements, mining and geological conditions, and technical and process requirements.
- Used the “ideal cycle” to optimise activities, set leading KPI targets for each employee and introduce daily and weekly performance reviews.
Results
- Crew development rates increased by up to 48%.
Example of the “Ideal Cycle” tool in use