Situation
Our client, a major mining company in Russia, was undertaking a large-scale programme to digitalise its underground mines. Among other solutions, the company had selected and installed MineSched for medium-term planning, along with dispatch systems. However, it had been unable to find a suitable digital tool that could quickly produce short-term plans covering periods from 10 days down to individual shifts and generate work assignments for use in the dispatch system. Our team was brought in to help resolve this problem.
What we did
- Developed automated algorithms for short-term mine planning based on 10-day targets from MineSched.
- Created modules to calculate equipment productivity and work quantities using drilling and ground support plans and equipment specifications.
- Created a database to store current tasks, calculations, the actual progress of mining work and the condition of mine workings.
- Built user interfaces and reports for all user groups.
- Developed and implemented systems for data exchange and integration between MineSched, 10-day and shift work schedules, dispatch systems and a newly developed tablet application for mine supervisors.
Results
- An 83% increase in the completion rate for issued work assignments.
Actual completion of issued work assignments, % of assigned work