Situation
Our client, the operator of a zinc deposit in the CIS, aimed to optimise the operation’s NPV. We were engaged to conduct a diagnostic, develop an optimal life-of-mine production profile, and identify measures to maximise the NPV of the deposit as a whole.
What we did
- Analysed development options and production constraints, and identified the drivers of NPV.
- Modelled an NPV scenario incorporating operational improvements—increased throughput at the underground mine and processing plant—with a total uplift of 24% against the base case.
- Proposed changes to the mining sequence for the deposit’s blocks, taking into account plans to develop new levels, equipment acquisition plans, ventilation constraints on each level and other factors.
- Held idea-generation sessions to address future production constraints and prioritised 3 NPV improvement initiatives with a maximum additional uplift of 11%. All the initiatives enabled the mine to increase production and mine out the deposit sooner.
Results
- Identified potential to increase project NPV by 35%.