Situation
Our client, a non-ferrous metals mine, was undertaking a planned capacity expansion, aiming to increase production from approximately 1 million tonnes a year to the maximum of 3.6 million tonnes a year specified in the original mine development plan. Our team was engaged to assess opportunities to increase the mine’s NPV through value engineering of the design, including opportunities to accelerate construction and optimise capital expenditure.
What we did
We identified potential to increase the mine’s NPV through 18 sets of initiatives across 5 main areas:
- Optimising scale: increasing the mine’s maximum capacity from 3.6 million tonnes a year to 4.5 million tonnes a year through initiatives to improve shaft hoisting availability and capacity and optimise the ventilation layout.
- Accelerating construction and bringing full production forward by 8 years through initiatives to accelerate mine development on the project’s critical path, reroute the decline, drive shaft-station connections in parallel and revise the mining sequence, including the order in which mining areas are developed.
- Reducing operating costs: using development waste rock alongside the backfill mix to reduce consumption of the mix, and optimising the productivity of mining equipment.
- Reducing capital expenditure by changing the ore transport layout to eliminate some of the capital development required for conveyor drifts.
Results
- A 276% increase over the base-case NPV.
Identified potential to increase NPV above the base case, RUB billion