Potential identified to bring a new longwall face into production 132 days earlier by increasing the mine development rate by 86%

Anton
Anton
Senior Partner

Situation

Our client, a major Russian coal producer, was behind schedule in bringing a new longwall face into production. Our team was invited to one of its mines to assess operational performance and identify opportunities to increase the overall mine development rate, accelerate preparation and bring the new face into production by the required date.

What we did

  • Identified opportunities to increase the overall mine development rate through 5 key levers: reducing cycle time, unplanned equipment repairs, unplanned conveyor repairs, organisational delays and process-related downtime
  • Developed a tool to prevent roof cavity formation and began implementing it to increase the extraction rate at the current longwall face and align it with the schedule for preparing the new face for production
  • Prepared recommendations to improve mine planning: an automated model to monitor the critical-path schedule for longwall preparation, and a weekly meeting to agree corrective action if target dates slipped
  • Assessed the business system team's skills and prepared a programme of the training required

Results

  • 132-day reduction in the time to bring the new longwall face into production
  • 86% increase in the mine development rate

Levers for achieving the potential mine development rate, %

Waterfall chart showing levers that raise the potential mine development rate to an index of 186