Situation
Our client, an iron ore mine using a descending-slice mining method in unstable, fractured ore, planned to increase production from 1 million tonnes of ore a year to more than 4 million tonnes a year. Our team was brought in to assess the expansion project and improve its NPV.
What we did
- Developed 98 initiatives through idea-generation sessions.
- Identified potential to increase NPV by RUB 5 billion by implementing 33 first-wave initiatives, which were handed over to the design institute for detailed design.
- Developed a plan to increase mine production while reducing capital expenditure.
Results
- 37% increase in project NPV.
- 98 initiatives developed.