Situation
Our client, an underground mine, consistently met its monthly production plan but struggled to meet its ore grade targets. The problem lay in the quality of monthly mine planning by section managers and in executing the plan with due regard to the grades in individual workings.
What we did
- Developed a monthly work schedule template for section managers, setting out ore dispatch tonnages and the workings in each section.
- Trained section managers to complete the schedule and developed criteria for an achievable monthly plan.
- Integrated the work schedule with the existing digital system for recording actual work volumes.
- Introduced a structured, effective meeting process with the mine director to review monthly plans once a month and assess adherence to the monthly plan 3 times a month, enabling corrective action.
Results
- Adherence to the monthly plan increased from 52% to 87%, measured as the percentage of tonnes from planned workings.
Work schedule