Situation
Our client, a large Russian mining and metals company, needed to increase mine development rates to prepare production faces. We were engaged to identify the main levers for accelerating development and implement corrective actions.
What we did
- Identified shift-change delays as the main opportunity to increase development rates.
- Developed a model to analyse data from the Flexcom positioning system and calculate the time lost to late arrivals and early departures.
- Optimised the schedule for crew transport vehicles.
- Worked with the mine transport team to eliminate delays to underground diesel locomotive services.
- Introduced posters in development areas explaining the disciplinary measures for arriving late at or leaving early from the workplace.
- Introduced daily reviews of late arrivals and early departures at morning meetings.
Results
- 20% increase in mine development rates.
Example of a report for tracking shift-change delays