Situation
Our client, a Russian underground mine using sublevel caving, was experiencing a decline in production. Its internal operational improvement team had implemented individual initiatives over five months, but without a significant impact. Production volume and metal grade targets were regularly missed. Our team was brought in to deliver rapid improvements and establish effective working practices in the project management office.
What we did
- Implemented a mine planning and reporting system covering monthly, 10-day, daily and shift horizons.
- Linked shift work orders to the mine’s monthly work plan and redesigned the system for setting and reporting against shift targets.
- Updated and agreed production plans to reflect the initiatives implemented.
- Developed a performance indicator framework across the production management hierarchy.
Results
- 30% increase in output.
- 36% increase in the mining rate.
- 3-percentage-point increase in metal grade in blasted ore.
September–October production rate, thousand tonnes