Situation
The team behind one of the largest heavy industry projects faced a sharp rise in construction costs. The reasons? Switching to new equipment types because of sanctions restrictions, redesigning as construction progressed, and delays in construction.
They came to us when a swift, well-judged solution was needed. The task was to optimise the project budget without compromising the mining and processing operation’s future performance. We joined as a partner to the project team: we helped review the scope of work and, together with the client’s team, optimised design quantities and prepared an updated budget.
What we did
- Identified and reduced excess quantities of work, accounting for 75% of the total savings.
- Reduced financing costs by accelerating construction, accounting for 10% of the savings.
- Removed some facilities with excessive specifications from the project, accounting for 6% of the savings.
- Deferred some work to the operating phase and optimised the cost of certain works.
- Handed over initiative charters, agreed with the design institutes, for the client to implement independently. An audit two years later showed that the client had implemented most of the initiatives and achieved actual reductions in the cost of the facilities under construction.
Result
- A 36% reduction in the project’s unspent budget.
Capital expenditure optimisation savings, RUB billion