Situation
Our client, a fertiliser producer in the CIS, was six months behind schedule on the construction of a new processing plant. Our team was brought in to work with the client’s team and contractors to deliver the project on time, introduce modern construction management methods and provide transparency.
What we did
- Shortened the construction critical path by 80 days.
- Quadrupled the pace of work on constructing the cellulose feed line, installing flotation piping and services, and installing tanks.
- Reduced the time needed to refine the design documentation by eliminating 20 project risks and minimising 14 others.
- Established a project control room.
- Introduced construction monitoring tools, a structured meeting schedule and tools for tracking key project indicators.
- Trained the capital projects team.
Results
- 230-day reduction in construction time.
- $1 million in cost savings.
Actual reduction in construction duration, days