Our client, a large mining and metals group, needed to increase mine development rates. The main way to accelerate development was to reduce downtime caused by organisational issues, particularly delays in material delivery because the suspended monorail track lagged behind the advancing face. There was no process for planning track beam installation at the face or monitoring it on each shift. Installation and replacement were carried out inconsistently, and procedures were communicated to personnel only as a formality. Our team was engaged to address these issues.
What we did
- Introduced a shift report on the gap between the face and supporting infrastructure.
- Introduced daily monitoring of the distance between the monorail track and the face, with improvement actions developed and tracked.
- Developed a step-by-step work instruction for replacing track beam sections, tailored to conditions at the mine and the materials and tools in use.
- Trained operational personnel.
- Displayed the work instructions in operational areas and at the face.
- Introduced weekly planning and daily monitoring of service extensions.
Results
- Up to 40% reduction in crew downtime caused by material delivery delays.