+900 kg of gold a year: diagnostic review and improvement roadmap for a regional division of a major gold producer
12.08.2026
Operational due diligence for a top-10 international gold producer: how to identify $500 million in operational improvements

Delivery times for strategic capital projects cut by 2–3 months by improving the management system of a Russian non-ferrous metals producer's capital projects department

Anton
Anton
Senior Partner
Anatoly
Anatoly
Associate Partner

Situation

Our client, a major vertically integrated Russian producer of non-ferrous metals, was carrying out two projects to expand a processing plant and a project to build a new gold processing plant. These projects were strategically important to the operation's development and were at different stages, from design to construction and installation. The client engaged our team to deliver a comprehensive improvement programme for the capital projects department's management system, using these three strategic projects as the basis.

What we did

1. Implemented a management system across the three strategic projects, comprising:

  • A cascade of internal meetings, including project control meetings, and external meetings for the shareholder.
  • Tools to track readiness for the start of construction and installation or other critical work, increasing the detail and scope of schedules by 200–300%.
  • Trackers for contractor procurement and equipment deliveries, with detailed monitoring of all milestones and their impact on the critical path.
  • A portfolio of more than 100 initiatives across the three projects to shorten delivery times and reduce project risks.

2. Refined the target project management structure and increased the proportion of filled positions from 68% to 84%.

3. Created an in-house project management methodology role to support sustained adoption and replication of the tools implemented.

Results

  • 118% increase in contractor workforce productivity on the grinding circuit expansion project, which was in the active construction and installation phase.
  • 78-day reduction in the critical path of the flotation and thickening upgrade programme, which was in the early stages of construction and installation.
  • 51-day reduction in the time to commissioning of the new gold processing plant, which was at the design documentation and detailed engineering stage.

Examples of results

Visual management boards used for project control meetings

Examples of detailed project schedules and Gantt charts

Examples of project tracking spreadsheets with colour-coded status indicators

Spreadsheets showing the portfolio of project improvement initiatives