+900 kg of gold a year: diagnostic review and improvement roadmap for a regional division of a major gold producer
12.08.2026
Operational due diligence for a top-10 international gold producer: how to identify $500 million in operational improvements

The initiatives developed helped increase the mining project’s NPV by RUB 48 billion

Situation

Our client, a vertically integrated mining group, engaged our team to implement initiatives to increase the NPV of one of its mineral deposits by accelerating construction of underground infrastructure and key surface facilities.

What we did

Implemented initiatives to increase NPV:

  • Increased capital development rates on the main decline by 20–66% across different rock stability categories by developing improvement initiatives and strengthening worker motivation.
  • Rerouted the decline through more stable rock to bring the mine to design capacity sooner.
  • Reduced delays against target commissioning dates for key project facilities by 5 months by developing measures to shorten the critical path for each facility.
  • Established and developed the operation’s own project management office team to manage construction.
  • Implemented a construction management system.

Results

  • An increase of RUB 48 billion in the deposit’s NPV.
  • An 8-year reduction in time to reach design capacity.
  • A 20–66% increase in capital development rates.
  • Commissioning brought forward by 5 months.

Results achieved for the mining project

Baseline and result comparison showing key facilities commissioned 5 months earlier

Capital development rate improvements of 20%, 55% and 66% for three rock stability categories

An 8-year reduction in time to reach design capacity and a RUB 48 billion increase in the deposit’s NPV