Managing the pace of design documentation delivery: from delays to systematic control

Portrait of a man wearing glasses and a dark polo shirt.
Anton
Senior Partner
Portrait of a man in a pale shirt with his arms folded.
Yury
Associate Partner
Portrait of a smiling man in a pale shirt.
Anatoly
Associate Partner
Portrait of a man in a white shirt with his arms folded.
Sergey
Consultant

On major capital projects, the time required for design is generally comparable to the overall project delivery timeframe. Ideally, construction should begin only once all design and detailed working documentation has been issued. In practice, however, companies often carry out construction in parallel with design and documentation delivery to shorten the overall project schedule.

In doing so, companies take on a range of risks associated with these two processes falling out of step. This slows construction and installation works and delays the release of work fronts. As a result, projects become more expensive as mobilised personnel and equipment stand idle, and fall behind their approved schedules.

In our view, design and construction fall out of step for three main reasons:

1. Documentation delivery priorities are not aligned with the construction and installation schedule. There is no clear link between the documentation delivery schedule and the construction and installation plan. Instead, documentation is developed and issued according to the resources the designer has available for particular sections of the design.

2. There is no day-to-day control of documentation delivery. Documentation development is planned and monitored in broad work packages. The client agrees a delivery deadline with the designer, but there are no mechanisms for checking progress along the way. In practice, control is limited to standard design meeting minutes.

3. The process for agreeing how review comments are resolved is unstructured. Comments on issued documentation following review with the client are recorded in emails, correspondence and meeting minutes. Once there are more than 10 comments, this approach makes it difficult for both the client and the designer to track their resolution.

These three problems create a vicious circle: the lack of a detailed plan and clear priorities prevents effective control, while a chaotic approval process compounds the problem, leading to missed deadlines. The result is constant firefighting, finger-pointing and rescheduling.

The solution is not to hold more meetings or put more pressure on the design company, but to introduce a system for day-to-day design planning and control. This system rests on three elements: detailed design planning, monitoring delivery against the plan, and tracking the resolution of review comments.

Dedicated construction companies can use comprehensive project management platforms such as Autodesk Construction Cloud, Procore and Oracle Aconex, which provide end-to-end functionality for coordinating design and construction. For industrial companies delivering individual capital projects, however, the cost and complexity of implementing these industry-specific solutions often make them impractical. Core planning and day-to-day control tasks can be handled through a combination of readily available tools: Primavera for detailed planning, Excel for tracking the pace of design work and, for example, Yandex Tracker for managing review comments.

Therefore, to manage the pace of documentation delivery effectively and avoid missed deadlines, the following tasks need to be addressed:

1. Develop a detailed design schedule linked to the construction and installation plan. Managing design against a high-level schedule does not resolve the issue of priorities. A detailed documentation delivery schedule is needed, with each section or even individual drawing directly linked to critical activities in the construction and installation plan. This schedule is the ‘gold standard’ for everyone involved, defining which documents are needed and in what sequence to keep construction moving without interruption. This addresses the lack of prioritisation.

2. Introduce regular, day-to-day monitoring of the pace of design work. Replace cumbersome meeting minutes with a documentation progress tracker for daily and weekly monitoring of compliance with the design schedule. This is a live document, updated daily by the designer and checked by a representative of the client's engineering team, showing:

  • The percentage complete for each section or drawing and for the project as a whole
  • The current status: ‘In progress’, ‘Under client review’, ‘Comments resolved’, ‘Issued for construction and installation’
  • Risks and critical deviations from the delivery schedule, taking the current status into account

This approach enables a shift from reactive to proactive management and addresses the lack of interim progress monitoring.

3. Formalise the process for agreeing the resolution of review comments through a comments register. Record all comments on design documentation in a central comments register rather than in emails. Each comment is assigned a unique number, a status (‘Open’, ‘In progress’, ‘Closed’), an owner and a resolution deadline. This gives the client and the designer a shared source of information, prevents comments from being lost and provides an accurate picture of documentation quality at any time. It addresses the lack of a clear process for agreeing the resolution of review comments.

A completed project for a Pieff client: improving control over the pace of design documentation delivery

Case study showing how engineering management tools reduced a processing plant project’s documentation submission delay by 30 days, with planned and actual cumulative progress.

Proactive use of design control tools eliminated the schedule slippage entirely: all documentation packages were prepared to a good standard and submitted for expert review by the mandated deadline. The volume of correspondence was reduced nearly eightfold, while meetings became shorter and more productive.