Situation
Our client, a Russian mining and metals operation, encountered difficulties organising construction and installation works for a gold processing plant. The company had no contracting strategy, including no principles for packaging the work into contract lots. It had also neither compiled a list of potential contractors nor established criteria for selecting qualified contractors. The client brought in our team to address these issues.
What we did
- Carried out a detailed risk assessment and developed and adopted an optimal contract packaging strategy to reduce the risk of a single contractor delaying the project.
- Compiled a register of 70 companies and carried out detailed assessments, including developing assessment criteria and negotiating with priority companies.
- Reviewed detailed construction strategies and project schedules with the top 5 companies, two of which prepared detailed work execution plans free of charge.
- Developed recommendations to address procurement blockers.
Results
- Brought commissioning forward by 30 days by accelerating procurement of construction and installation works.
- 12 companies were registered in advance to participate in the construction and installation tender.